Following several successful station cleaning and maintenance blitzes in Spring/Summer 2021 and Spring/Summer 2022 - SEPTA is continuing the initiative beginning May through September 2023 on the Broad Street Line (BSL) and Market-Frankford Line (MFL).
Efforts will focus on maintenance - including work on elevators - as well as painting, power washing, and installing enhanced lighting and new signage.
For each blitz - stations will close at 8PM on Friday and reopen at 5AM the following Monday. The elevators will be out of service.
During the closures - customers can find alternate service at neighboring stations on the Broad Street and Market-Frankford Lines or on nearby bus routes.
Work will start the weekend of May 5, 2023 at Snyder Station on the Broad Street Line (BSL) - then move to:
Allegheny (MFL) |
Friday, May 19, 2023 |
Tioga (MFL) |
Friday June, 16 2023 |
11th (MFL) |
Friday, July 14, 2023 |
Somerset (MFL) |
Friday, July 28, 2023 |
Hunting Park (BSL) |
Friday, August 11, 2023 |
34th (MFL) |
Friday, August 25, 2023 - Postponed to Friday, October 22, 2023 |
Logan (BSL) |
Friday, September 8, 2023 |
46th (MFL) |
Friday, September 22, 2023 - Postponed due to weather |
13th (MFL) |
Friday, October 6, 2023 |
Again - for each blitz - stations will close at 8PM on Friday and reopen at 5AM the following Monday. The elevators will be out of service.